Vermont mechanics lien deadlines for contractors

A plain-English summary of how a contractor, subcontractor or supplier protects payment with a mechanics lien in Vermont. Last checked 2026-10-05. This is general information, not legal advice. Verify with your attorney before you rely on any deadline.

The rules at a glance

  • Who: contractors; subs/suppliers who give notice (9 VSA 1921)
  • NTO: subs/suppliers written notice to owner, no day count; lien limited to unpaid contract price. NOC: none
  • Claim: memorandum with town clerk; lapses 180 days after last payment due (1921, 1923). Foreclosure: 180 days of filing (1924)
  • Waiver forms: none; advance waivers unenforceable. Residential: homesteads covered (1927)

Source and last verified

Official source: https://legislature.vermont.gov/statutes/chapter/09/051. Last verified 2026-10-05. Deadlines often differ for residential and commercial projects and change when the law changes. Verify with your attorney.

How BossHours helps

BossHours loads state rules into the app and shows a verify-with-your-attorney note beside each one, so notices and waivers are prepared from your job records. It does not give legal advice.

Try BossHours free for 7 days

Field Hours $149, Office Hours $379 and After Hours $499 a month. Unlimited users on every plan, no setup fee, month to month, 7-day free trial.

Start your free trial
Vermont mechanics lien deadlines for contractors