BossHours

South Carolina mechanics lien deadlines for contractors

A plain-English summary of how a contractor, subcontractor or supplier protects payment with a mechanics lien in South Carolina. Last checked 2026-10-05. This is general information, not legal advice. Verify with your attorney before you rely on any deadline.

The rules at a glance

  • Who: laborers, mechanics, subs, suppliers with owner authorization (29-5-10, -20)
  • NTO: sub-sub/supplier lien capped unless notice of furnishing to contractor (29-5-20(B)). NOC: optional notice of project commencement within 15 days (29-5-23)
  • Claim: serve owner and file sworn statement within 90 days (29-5-90). Foreclosure: suit within 6 months of last work (29-5-120)
  • Waiver forms: none found. Residential: none found

Source and last verified

Official source: https://www.scstatehouse.gov/code/t29c005.php. Last verified 2026-10-05. Deadlines often differ for residential and commercial projects and change when the law changes. Verify with your attorney.

How BossHours helps

BossHours loads state rules into the app and shows a verify-with-your-attorney note beside each one, so notices and waivers are prepared from your job records. It does not give legal advice.

Try BossHours free for 7 days

Field Hours $149, Office Hours $379 and After Hours $499 a month. Unlimited users on every plan, no setup fee, month to month, 7-day free trial.

Start your free trial
South Carolina mechanics lien deadlines for contractors