Ohio mechanics lien deadlines for contractors
A plain-English summary of how a contractor, subcontractor or supplier protects payment with a mechanics lien in Ohio. Last checked 2026-10-05. This is general information, not legal advice. Verify with your attorney before you rely on any deadline.
The rules at a glance
- Who: original contractors, subs, suppliers, laborers (ORC 1311.02)
- NTO: notice of furnishing within 21 days of first work (1311.05). NOC: owner records before work and posts (1311.04)
- Claim: affidavit within 60 days of last work for 1-2 family dwellings, otherwise 75 days (1311.06). Foreclosure: lien lasts 6 years (1311.13); void if no suit within 60 days after notice to commence suit (1311.11)
- Waiver forms: none. Residential: 60-day filing, 1311.011
Source and last verified
Official source: https://codes.ohio.gov/ohio-revised-code/chapter-1311. Last verified 2026-10-05. Deadlines often differ for residential and commercial projects and change when the law changes. Verify with your attorney.
How BossHours helps
BossHours loads state rules into the app and shows a verify-with-your-attorney note beside each one, so notices and waivers are prepared from your job records. It does not give legal advice.
Try BossHours free for 7 days
Field Hours $149, Office Hours $379 and After Hours $499 a month. Unlimited users on every plan, no setup fee, month to month, 7-day free trial.
Start your free trial