Nebraska mechanics lien deadlines for contractors
A plain-English summary of how a contractor, subcontractor or supplier protects payment with a mechanics lien in Nebraska. Last checked 2026-10-05. This is general information, not legal advice. Verify with your attorney before you rely on any deadline.
The rules at a glance
- Who: anyone under real estate improvement contract (52-131)
- NTO: optional notice of right to assert lien (52-135); caps lien against protected owner (52-136). NOC: optional (52-145)
- Claim: 120 days after final furnishing (52-137). Foreclosure: enforceable 2 years after recording (52-140); lapses if no suit within 30 days of written demand
- Waiver forms: none (52-144). Residential: protected-party rules (owner-occupied, up to 4 units)
Source and last verified
Official source: https://nebraskalegislature.gov/laws/statutes.php?statute=52-137. Last verified 2026-10-05. Deadlines often differ for residential and commercial projects and change when the law changes. Verify with your attorney.
How BossHours helps
BossHours loads state rules into the app and shows a verify-with-your-attorney note beside each one, so notices and waivers are prepared from your job records. It does not give legal advice.
Try BossHours free for 7 days
Field Hours $149, Office Hours $379 and After Hours $499 a month. Unlimited users on every plan, no setup fee, month to month, 7-day free trial.
Start your free trial