Arizona mechanics lien deadlines for contractors

A plain-English summary of how a contractor, subcontractor or supplier protects payment with a mechanics lien in Arizona. Last checked 2026-10-05. This is general information, not legal advice. Verify with your attorney before you rely on any deadline.

The rules at a glance

  • Who: licensed contractors, registered professionals, subs, suppliers, laborers (ARS 33-981)
  • NTO: 20 days after first furnishing, to owner, original contractor and lender (33-992.01); wage laborers exempt. NOC: none required; owner may record notice of completion (33-993)
  • Claim: 120 days after completion, or 60 days after recorded notice of completion (33-993). Foreclosure: 6 months after recording + lis pendens (33-998)
  • Waiver forms: yes, 4 statutory forms (33-1008). Residential: no lien on owner-occupied dwelling unless claimant contracted directly in writing with owner-occupant (33-1002)

Source and last verified

Official source: https://www.azleg.gov/ars/33/00993.htm. Last verified 2026-10-05. Deadlines often differ for residential and commercial projects and change when the law changes. Verify with your attorney.

How BossHours helps

BossHours loads state rules into the app and shows a verify-with-your-attorney note beside each one, so notices and waivers are prepared from your job records. It does not give legal advice.

Try BossHours free for 7 days

Field Hours $149, Office Hours $379 and After Hours $499 a month. Unlimited users on every plan, no setup fee, month to month, 7-day free trial.

Start your free trial
Arizona mechanics lien deadlines for contractors